Sunday, July 13, 2014

Preparing Engine room for dry dock.

25 Important Points to Consider While Securing the Engine Room for Dry Docking

Once the vessel enters the dry dock for hull inspection, it is important that the ship’s engineer secure the ship’s propulsion plant and the engine room in the correct sequence to prevent any kind of damage or problem while restarting the plant once the dry docking of the vessel is finished.
Following points must be considered once the ship enters the dry dock and before emptying the water from the dock to rest the ship on the keel blocks:
1. Ensure all the tanks in the engine room are at required level as demanded by the chief officer to achieve required trim for docking.
Related reading :
Maintenance of small tanks in the ship’s engine room , List of some important tanks on shipList of fuel, diesel, and lube oil tanks on ships.
2. Shut down all the auxiliary engines except one for providing the required power
Related Reading:
Procedure for starting and stopping generatorsImportant signs indicating auxiliary engine needs overhaulingA step-by-step guide to overhauling generators on ships.
3. Isolate sequential start system for generators
Related Reading:
How to synchronize generators on ships?Important points to consider while carrying out alternator maintenance of ship’s generatorImportant points for major overhauling of ship’s generator
4. Shut steam to jacket cooling water system
drydock
Related Reading:
General Overview of Central Cooling System of Ships
5. Keep the jacket cooling water pump running  until the main engine is gradually cooled down
6. Transfer the main engine lube oil in the sump to lube oil settling tank by using purifier
mairne engine
Related Reading:
Ways to optimize lube oil usage on ships
7. Ensure all auxiliary engines are shut down except one diesel engine supplying enough power
8. Before shutting down all the auxiliary engines, ensure they are changed over to diesel oil
Related Reading:
Fuel oil change over procedure
9. The main engine should be changed over to diesel oil prior one hour of docking. If not, changeover to diesel oil with fuel oil service tank return valve open until line has been flushed with diesel oil
10. Shut down lube oil and fuel oil purifiers
11. Shut down deck machinery system and isolate it from main switchboard
Related Reading:
Safety Devices for Main Switch Board 
12. Shut down and isolate the auxiliary boiler. Allow it to cool naturally and once the pressure is below 1 bar, open the vent
Related Reading:
Shutdown procedure of boiler
13. Once the boiler is shut down, stop and isolate the feed water system and distillate tank
14. Circulate diesel oil in the boiler fuel pipeline system before shutting down the fuel oil pumps
15. Shut down the stern tube lube oil system and if required, drain the lube oil system back to stern tube storage tank
16. Shut down the accommodation air conditioning system and refrigeration plant until the shore supply is connected to the ship
Related Reading:
8 Common Problems Found in Ship’s Refrigeration System
17. Shut the steam to the alorifier and switch on the electrical heating system
18. Ask shore in-charge for water connection required for running air conditioning and refrigeration system
19. Isolate ship’s fire pump and connect the shore fire connection to ship’s fire line
Related Reading:
What is international shore connection?
20. Check the frequency, voltage and phase sequence of the shore power
21. Isolate emergency generator before connecting shore power
Related Reading:
Ways of Starting and Testing Emergency Generator 
22. Shut down the running generator leading to blackout for connecting shore power
23. Connect the shore power to emergency switchboard
Related Reading:
What is cold ironing?
24. Restart the jacket water pump for the generator until it is gradually cooled down to avoid thermal stresses. Once cooled, shut the pump
25. Secure the engine room fire fighting system including foam and CO2 fixed fire fighting system
Related Reading:
Mistakes not to make while handling CO2 Fire Fighting System
Inform the dry dock in- charge that engine room is ready for docking and dock water can be emptied.
Is there any other important points that should be added to the list? Let us know in the comments below.
For complete procedure of various dry dock operations for Engine Room Department, check out our ebook:
A Guide to Master Dry Dock Operations (For engine room department) is a downloadable ebook designed to help you understand the whole dry docking procedure is a step-by-step manner, right from the planning to sea trials.

How to know Generator need to overhaul

8 Signs That Indicate Your Ship’s Auxiliary Engine Needs Overhauling

Ship’s auxiliary engines are the most important supporting pillars that keep the ship going. As a marine engineer working on ships, understanding the ship’s auxiliary engines is of prime importance in order to avoid sudden breakdowns or blackout situation.
However, ship’s auxiliary engines are not easy to tame. They need constant monitoring and maintenance for running at all the times and for preventing them from bringing the ship to a stand still.
Though routine maintenance and checks of auxiliary engines is a must, there are times when they  requires serious overhauling. As marine engineers, it is important to know the time and signs which tells that the auxiliary engine needs overhauling.
Mention below are eight signs to check in your auxiliary engine.
1. Generator Not Taking Rated Load
If the generator is not taking the rated load then there are chances that it is having some serious trouble. Signs like overall temperature of the engine going off-limit, important parameters showing abnormal figures and unusual fluctuations etc. indicates that the generator needs some serious checking.
generator overhauling
2. Power Imbalance
A ship’s engineer must keep a close eye on all the parameters, especially while taking performance readings of the auxiliary engine. If there is high peak pressure variation in any of the generator units as compared to the average pressure, it indicates that the combustion chamber needs immediate overhauling.
3. Degradation of Lube Oil
Examining the quality of the lube oil is yet another way to find out about the condition of the ship’s auxiliary engine. If it is found that the lube oil is degrading and needs to be removed before its running hours limit due to sludge formation, it may indicate blow past of the units. Such condition would require finding out the faulty unit followed by major overhauling.
Degradation of lube oil would also lead to choking of filters, major reduction of oil pressure, and sudden increase in differential pressure. It is important to keep a track of these signs as well.
4. White Metal Particles Found in Filters
If any type of metal particles (small or large) are found in the filters, it indicates that major wear-down of bearings is taking place. This would require immediate overhauling of the faulty unit.
5. Unusual Knocking Sound
Sound of the auxiliary engine is also one of the best ways to identify a problem. As a marine engineer working on ships, you would be quite familiar with the usual working sound of the auxiliary engine. If the “working sound” is replaced by any unusual knocking sound, it indicates that there is some problem with your machinery system.
Observe the knocking sound closely, if the sound is increasing at a faster rate, it is better to rectify the faulty engine as soon as possible.

6. Generator Over-Speeding
Over-speeding of generator is a situation wherein uncontrolled acceleration of the engine takes place, leading to mechanical failure and serious accidents. Mostly, it occurs during the time of starting, but can also occur when it is running on load due to fuel pump getting stuck or problem in the fuel system. Check if your engine is over-speeding and take measures accordingly.
7. Abnormal Crankshaft Deflection Readings
A marine engineer has to take timely measurement of crankshaft i.e. crankshaft deflection with the help of dial gauge. If the readings are above the normal limit, it indicates problem in the main bearings or alignment of crankshaft, requiring immediate action.
8. Running Hours 
Last but not the least, keeping a track of the running hours is extremely important to know when the engine would require next overhauling. Read the past records and carry out timely overhauling procedures.
These are some of the important points to figure out if your auxiliary engine requires complete overhauling. Do you any other ways to find out problem with auxiliary engines? Let us know in the comments below.
D’carb or major overhauling of a ship’s generator is a very tedious task for marine engineers on board. Following a step-by-step procedure backed by systematic planning is the base of a successful generator overhauling procedure.

Knowledge for onboard inspection

The best way to deal with fires on board ships is to prevent them rather than letting them occur. Breaking out of fire in a place where no fire exist is called “ignition”, whereas “flash” is a term used for fire eruption in a new place as a result of flames from an existing fire in a nearby place (the ignition source).

Fires on board ships can be prevented by finding and rectifying leakages of fuel oil, lubricating oil, and exhaust gases.

In a ship’s generator room, the biggest danger of fire is from a leaky high pressure fuel pipe. Oil leaking from such pipe can fall on high temperature exhaust manifold or on indicator cocks, which are sensitive points for catching fire.
In modern marine engines, there is push-type cover concealing the indicator cocks; however in old engines there is no such provision available which makes it quite difficult to provide lagging to indicator cocks.
These days fuel high pressure pipes are sheathed and the leakage finds its way to a small tank at the bottom of the engine known as fuel leak off tank. It is imperative to keep this system in good order by regularly testing the tank alarm – fuel leak off tank high level alarm.
Leakages are mainly caused because of pipes breaking due to vibrations, clamps rubbing against pipes to create holes, pipe connections behind the pressure gauges getting damaged due to ageing (we generally do not look here), leakages from fittings at boiler furnace front and incinerator front etc. These leakages are some of the most common “hot spots” for fire. Moreover, careful and periodical checks are also required on boiler smoke side and incinerator uptake.

Fires can be largely prevented by providing effective laggings to hot surfaces such as generator turbocharger bellows, main engine exhaust uptakes after the turbocharger, various steam pipes and pipes carrying hot oil. Laggings can be done by ship staff but these days specialist contractors are available to carry out this work more aesthetically. Also, whenever lagging is removed, a habit should be cultivated to put it back after the work is finished.
Apart from this, it is also important to check/test fire detectors on regular basis. Some of the main types of detectors used on ships are:
Flame detectors 
Light produced by a flame has a characteristic flicker frequency of about 25Hz. The spectrum in the infra red or ultra violet range can be monitored to give an alarm. Oil fires generally do not give off much smoke and this type of sensor is preferred, especially near fuel handling equipment or boilers to give an early warning.
Heat detectors
Heat detectors are of various types such as rate of rise type, which has bi-metallic type detecting elements – a thick strip and a thin strip. The thin strip is more sensitive to temperature rise than the thicker one.  If there is a sudden rise in temperature, the thin one bends faster than the thicker one, bringing both of them in contact.

During normal temperature rise both strips will deflect about the same amount and thus show no reaction. Normally if rate of rise is less than 10 deg C in half an hour, the detector will not give any alarm. If the rate should rise to 75 degree Celsius, or more, the two strips come in contact, thus triggering the alarm.
Smoke detectors
There are two main types of smoke detectors used
1) Light obscuration type
2) Ionization type Liquid or gas fires may not give off smoke initially but will catch fire spontaneously. Thus smoke detectors are not effective for such fires. These detectors are mostly used in accommodation areas.
Important points to consider for fire prevention on board ships
  • In engine room, waste bins used for storing oily rags must have lids (covers). Oily rags should not stay lying around or stuck at unnecessary places. Receptacles with covers should be provided at each floor and on both sides.
  • High pressure fuel oil pipes should not be tightened to control a leakage while the engine is running. Also, oil shouldn’t be taken in to turbochargers during operation.
  • Short sounding pipes should be kept shut with plugs. Never should they be left in open position for the sake of convenience. Cases have been reported wherein oil has spilled out from these short sounding pipes leading to accidents.
  • Loose pet cocks /small cocks on common rail pipes should be checked for.
  • Exhaust leakages and steam leakages should be promptly attended.
  • Ship’s crew should be careful about galley fires, especially by keeping electrical equipment in good order. Senior officers should keep an eye in the galley when provision is being received because this is the time when galley remains unattended for a long time.
  • One of the patent methods of fire prevention is effective and regular fire patrol. There is no method that can beat physical monitoring.
  • Fire caused by cigarettes is still one of the most common causes of fire. All care should be taken to dispose cigarettes (using self closing ashtrays) and never should one smoke in bed.
           
  • Fires have also caused during loading and unloading of cargo such as coal. For this reason, ship personnel must always discuss the characteristics of the cargo and preventive methods to be taken during safety meetings and weekly drills.
These are some of the main points one needs to consider for a safe environment on ship. This list might not feature all the methods to prevent fire; however it does provide a brief overview of how things are to be handled on board ships.
Do you have more useful tips to prevent fire on board ships?
Image Credits: exportlogisticsguide, maritimesafety, expedo

Wednesday, July 2, 2014

Making Sure Steam Piping Is Safe(10 Simple Rules and Things to Look For)#.U692uodzWi0.facebook

Making Sure Steam Piping Is Safe(10 Simple Rules and Things to Look For)#.U692uodzWi0.facebook

Making Sure Steam Piping Is Safe(10 Simple Rules and Things to Look For)

Tue, 06/28/2005 - 7:42am
This document seeks to provide methods for screening high pressure (below 300 psig) piping systems, that may normally be encountered in industrial steam plants, to identify safety issues related to the design and/or installation of pipe, valves, flanges, and components used in these systems. The following is not an all inclusive guide to safe practices, but instead attempts to give some insight for understanding and conducting a simple screening of a steam piping system. This review of what is installed is important for every steam plant operator to help make sure that an unexpected accident is not waiting the next time someone opens a valve or puts a steam line into service.

1. Steam Piping Ratings of Boiler Systems
In most states and jurisdictions, steam piping is classified as high pressure piping when it exceeds 15 PSIG. The main construction code used to define high pressure piping issues and requirements for construction and installation is published by the American Society of Mechanical Engineers (ASME) Section I (Power Boiler) and ASME code B31.1 (Pressure Piping) codes. You can obtain copies of these code sections at www.asme.org or by calling 1-800-THE-ASME.

2. MAWP - What is it?
The piping, valves, and components of any high pressure piping system have to be rated for the MAWP, or the Maximum Allowable Working Pressure, of the boiler. ASME requires a nameplate be affixed to the boiler with this information on it. The piping attached to the steam discharge flange must also be built to withstand the MAWP that the boiler can generate. In multiple boiler installations, the design rules typically apply to all piping through the second stop valve from the discharge flange of the boiler and are governed by ASME Code Section I and B31.1. After the discharge of the second valve, the piping must be rated as required by the applicable jurisdiction. This may be the MAWP of the boiler or at least the setpoint of the highest safety relief valve protecting the system. There are also specific rules for stamping or identifying the piping which falls within the code boundary jurisdiction of the boiler. Typically the S/N (serial number), Certified By and Pressure will be stamped or a nameplate banded to the pipe indicating this information.

3. Some Piping Basics
It is very important that you understand what you are looking at and the consequences of being wrong when it comes to evaluating piping systems. Let’s start with the pipe itself. Most pipe you will ever encounter starts its life at a steel mill in sheet form. In many cases, the mill rolls the sheet into tubes and welds it. There are different piping designations, an example is ASTM A 53B, ASME SA 53 B. ASTM means American Society of Testing Materials, (www.astm.org), SA 53 B, is the designation for plain black steel pipe mostly used in the industry. Piping also comes in different schedules (or wall thicknesses). The schedule or thickness would be schedule 40 or 80. The wall thickness for typical 6 inches schedule 40 increases from 0.280 inches to 0.432 inches for schedule 80. Schedule 40 is what’s commonly called for in B31.1 for pressure piping in service conditions that apply to this article. B31.1 and ASME code, Section I, have calculations that the designers would use to determine the safe working pressure of the piping based on its type, thickness and minimum diameter. Schedule 80 is called out as good practice for most condensate systems since they are a severe duty as compared to steam. Condensate is likely to contain carbonic and or other mild acids. This tends to erode condensate piping over time. Making this kind of piping thicker from the start builds in a factor of safety.

4. Flanges and Their Ratings
You also need to be aware of flange pressure ratings. The ratings and certification information are usually stamped on the circumference of the flange. A 150 LB flange indicates a pressure temperature rating. This is not the MAWP of the flange, but a designation which allows a certain pressure use based upon the installation and temperature to be encountered. Pressure /Temperature ratings can be found in ASTM A 105 B 16.5 specification tables (www.astm.org).

5. Flange Materials
Flange materials can also be tricky. You always want to make sure you are using carbon steel flanges with the proper rating, A 105 B 16.5 is a typical carbon steel flange used in pressure piping applications. Cast Iron flanges are too brittle and could break in this kind of application.

6. Fastener Issues, When a Bolt is Not Just a Bolt
Fasteners could be another problem area. Fasteners should be rated to at least a grade 8. This means they have a tensile strength that could withstand the force that must be applied for the proper assembly of the components. There is also a standard marking system for fasteners. When you look at a bolt head you should be able to see markings that identify its grade or rating. Be aware that cheap fasteners can mean forgeries that can cost someone their life. You can find out more about fasteners and ratings by going to the National Fastener Distributor Association’s website at www.nfda-fastener.org. Also, be aware of threaded rods and studs. Studs are not simply some supply house off the shelf threaded rod cut to size. Studs should be marked with a stamping in the end that indicates they are a special grade and type of material that is of sufficient tensile strength. They might have a marking like “AB or HV” stamped into the end.

7. Joints and Joining Methods
Pipe gets assembled to other pipe, fittings, and flanges by either welding or threading. There are specific code requirements that describe when it is permissible to thread or when welding must be used. Within the welding world, you also need to be aware of several other possibilities. Flanges and fittings come as either slip on or weld neck. Slip on fittings are just that, slipped onto the end of the pipe. The flange is then welded up around the contact points on the inside and outside of the pipe and the flange. Slip on flanges are not considered as strong a joint as weld neck or butt welded connections. In the case of a butt welded or weld neck flange the two pieces, flange and pipe, are prepped and then welded together with full penetration through the weld construction (a welder carefully lays a bead and builds up layers around the entire surface of the gap between the two pieces). Socket welding is a term used to describe when a slip on fitting, usually used for small diameters, is inserted into the fitting until it bottoms out. Then the pipe is pulled back from the bottom and welded to the fitting. Failure to pull the pipe back can cause welds to fail from stresses.

8. Valve and fittings ratings
Valves and fittings should have their pressure rating cast into them or marked as required by the applicable material specification. Many pipe fittings are marked with a manufacturer’s logo or insignia, size, and schedule rating (example 6 inches SA 234 Gr WPB or 1 inches 3000M A105 B 16.5 with the logo). The pressure rating must be at least equal to the design MAWP. Again ASME/ASTM SA/A 234 or SA/A 105 B 16.5 give the specific requirements for these fittings. Valves will also be marked with their pressure rating along with the type of service permitted to be used. The ASME codes specify which types of valves and fittings are permitted to be used and their proper service applications in pressure piping applications.

9. Welding Considerations
Welding on pipe, fittings, flanges, and pressure vessels must only be done by someone with the proper credentials. Welding on pressure piping must be performed following qualified welding procedure specifications. It is the responsibility of the installer to have welding procedure specifications that are certified to meet the applicable ASME code construction;(refer to ASME code Section I and B 31.1 and ASME Code Section IX for welding procedure specifications). The National Board Inspection code which is required for repairs of pressure equipment also includes AWS (American Welding Society, www.aws.org) standard welding procedures. Every detail of AWS standard welding procedures must be followed when welding or the weld can be deemed to not be a qualified weld and in jeopardy of having to be removed.

10. Qualified People
Welders must also be qualified to the requirements of ASME code Section IX. Once qualified and certified, the welder can only weld within the variables listed on their welder’s performance qualification record. The welder must also weld within the process at least once every 6 months or the qualification expires. Records must be kept to prove that the welder had welded at least once every 6 months. Welders will mark their welds with stamping to identify which person welded which joint. This stamping could be there on your system but possibly obscured with insulation.

Along with the ASME required stamping, the National Boards registration numbers might also be found. The National Board of Boiler and Pressure Vessel Inspectors is located in Columbus, OH. They maintain a database of all registered pressure items. You can call them with the National Board number, original manufacturer and year built as indicated on a nameplate, and they can tell you lots about what you have and the original design. They can be reached at www.nationalboard.org. This is very important when inspecting, repairing or replacing items. The proper repair or replacement should ensure the same safety integrity as when the boiler, pressure piping or pressure equipment was originally constructed (If not better).

There it is 10 simple rules that might keep you or someone else alive. Trust me, you do not want to be around a piece of piping or a flange that lets go. We are talking the immediate removal of flesh, displacement of oxygen, and burns over so much of your body that it will be over in a painful matter of hours. This stuff is nothing to play with so make sure the job is being done right, use professionals, and know what you are getting. Also, take a little time to use the information above and know more about what you already have.

By John R. Ruskar and Mark Rudek

Monday, January 13, 2014

Don't underestimate UV light.


                             Ultra violet light caused eye injury

Whilst changing the ultra violet (UV) lamp in the ship’s fresh water steriliser unit, a crewmember inadvertently switched on the UV light and stared directly into it. Later on in the day, he experienced irritation, redness, pain and temporary blindness in the eye. He was given first aid on board and subsequently was sent ashore for treatment.

Result of Investigation1 The crewmember was not wearing appropriate personal protective equipment (PPE), such as the shaded UVEX glasses which were available on board and would have filtered the UV light;
2 The crewmember did not read the warning notice posted at the site, which outlined the hazards of UV light.

Root cause /contributory factorsNon-compliance with procedures:
1 No risk assessment was carried out to understand the hazards related to the task;
2 Lack of compliance with the company PPE matrix.
Ultra Violet

No excuses for hydraullic system. Pay attention to reopen the valves which was closed.



                         Injury from burst hydraulic valve  

On a cargo vessel in drydock, the crew was testing the operation of an electro-hydraulic mooring winch after completion of repairs. The team, led by the C/E, and comprising of the 3/E, J/E and an OS, entered the hydraulic machinery room and started the main pump motor. Without warning, the return line gate valve before the filter disintegrated and the detached bonnet flew through the air, hitting the J/E on his face and fracturing his skull and nose. He was immediately hospitalised ashore. Very fortunately, he narrowly escaped more serious injury that could have resulted in permanent damage to the eyes and brain and was able to recover fully from this accident.

Result of investigationDuring an earlier trial, it was noticed that one of the valve flanges next to the filter was leaking. After isolating the line, the crew renewed the gasket, and then opened the valve before the filter, but forgot to open the one after the filter. When the pump was subsequently started, the sudden build up of high pressure on the upstream side of the valve resulted in its violent disintegration.

View of broken valve Corrective action

Line diagram

Lessons learnt1 It is extremely important that, before commissioning hydraulic systems, all line valves are verified to be fully open and the system is thoroughly purged of air and primed with the correct quantity/type/grade of hydraulic fluid;
2 Return lines are not designed to take high pressure in most hydraulic systems.

Corrective/preventative actions1 The second valve (after the filter) was considered redundant. It was removed and replaced with a spool piece, reducing the risk of the inadvertent closure of the return line;
2 A sign was permanently installed next to the hydraulic pump motor starting switch warning personnel to ‘Ensure all return line valves are fully open’.

Take care electrical epuipments when U are to work with water.

                                      Fire on electrical transformer
The C/E, fitter and oiler were engaged in the routine maintenance of the common cooling water system of the ship’s refrigeration plant and air conditioning plants. While they were opening up the condenser cooling water line, due to a leaking line valve, a large quantity of water spurted out and fell on the main power transformer located directly below. A fire started around the transformer and there was an immediate blackout. The crew put out the fire by using a portable CO2 extinguisher.
Root cause/contributory factors1 System failure: company procedures did not contain specific instructions on carrying out work on refrigeration and heating, ventilation and air-conditioning (HVAC) systems;
2 Defective equipment: section valve in the cooling water line was leaking in shut position;
3 Inadequate risk assessment: cooling water line should have been blanked and drained before disconnecting;
4 Inadequate work planning; electrical equipment directly below work site was not protected against likely discharge of water.
Corrective/preventative actions (post-incident)1 Defective valve in cooling water line was replaced;
2 QHSE safety bulletin on the incident issued to the fleet;
3 New SMS procedure and risk assessment checklist created with guidelines on cleaning and maintenance of cooling water systems.

 

How to take pressure test to Fresh Water Generator safely When It was suspected in leakage.

Minor repairs had just been completed on the shell plate of the fresh water generator (evaporator) by a shore workshop while in port. As an original spare was not available, the damaged sight glass was substituted with a disc cut from a 5 mm thick acrylic sheet.
Upon restarting the plant after sailing, it was observed that the drum chamber was not developing sufficient vacuum. The ship’s engineers decided to carry out a pressure test of the casing to locate any leaks. Without considering the hazards, the crew introduced compressed air into the vessel and raised the internal pressure to about 3 bar. Suddenly, the acrylic sight glass shattered, injuring the electrical officer, who was applying soap solution to the shell’s exterior.
Lessons learnt1 It is very unsafe to subject vessels, tanks or containers to uncontrolled pneumatic pressure for testing purposes as there is great risk of permanent deformation or violent rupture;
2 A controlled hydrostatic test i.e. filling up the container with water to a permissible head (preferably under Class supervision) is the most appropriate and safe method for leak testing on board;
3 When a pneumatic test is considered the only practicable method, compressed air must be admitted through a suitable reducing arrangement and pressure must be closely monitored by a manometer/water column gauge, ensuring safe limits are never exceeded;
4 Fresh water generators should ideally be tested by creating an internal vacuum and applying a liquid dye externally on suspected areas.

Thermal Oil boiler explosion because of bent needle valve and using D.O

                          Crew injuries from oil heater explosion

Over a period of two days at anchor, one of the two vertical thermal oil heaters of a product tanker was observed to be not firing reliably. The crew opened and cleaned the burner unit and also adjusted the igniter electrodes twice, but after the second attempt, the heater refused to fire. On the third day, the C/E discussed the remedial action plan with the crew. They opened up the burner unit and cleaned the burner lance and igniter electrodes again. This time, the heater operated for about 90 minutes (eight firing cycles), after which it again failed to ignite. Resuming work after lunch, the electrician re-inspected electrical systems while the 3/E and cadet dismantled and cleaned the burner lance and nozzle unit, reassembled it under the C/E’s supervision and refitted it to the heater one more time.

When the test firing commenced, the 3/E, cadet and electrician positioned themselves on the top of the heater to monitor the automatic starting and firing sequence. The forced-draught fan went through a four-minute purge programme, but when the igniter sparked, there was a violent explosion.
The explosion lifted the thermal oil heater casing top, snapping most of the securing bolts. The burner arrangement was pushed out of alignment and the inspection cover was torn from its securing bolts. The ducting from the externally mounted forced-draught fan was torn apart at the flexible insert. Fuel lines running across the top of the thermal heater were deformed, and at least one began to leak from a weakened joint. The explosion triggered the engine room fire detection system, initiating a fire alarm on the panel at the fire control station, and also activated the local automatic water mist system. The three persons on top of the heater suffered burns over large portions of their bodies as the flame front engulfed them momentarily, but they were able to walk from the area to the accommodation. They were assisted by the mustered crew, who removed the remnants of the burnt coveralls and ill-advisedly pierced and drained (lanced) the blisters before placing dressings on the burns. The injured persons were also given painkillers and water to drink but remained seated in a cabin despite being in severe pain and trauma.

About half an hour after the explosion, the Master reported the incident to the port control and his local agents and requested medical assistance. Unfortunately, his request for helicopter evacuation (medevac) was initially denied due to the mistaken assumption ashore that helicopter operations over a tanker that had just suffered an explosion would be hazardous. Subsequent miscommunication between the response teams on shore added to this delay.

Paramedics boarded by launch about an hour after the accident and after rendering further medical treatment, they insisted on immediate evacuation of the casualties by helicopter. Eventually, after another hour, the men were winched off and conveyed to a shore hospital.

Result of investigation
1 The burner nozzle had been incorrectly assembled, probably during the several investigation and repair attempts. As a result, the needle valve stem became bent and due to an improper seal, the circulating fuel continued to spray into the furnace during the pre-ignition start sequence;

2 The crew, except the C/E, had very limited experience in servicing this equipment;
3 The manufacturer’s manual was poorly written, and lacked a clear drawing of the burner, details of spare parts, instructions for troubleshooting, servicing, inspection or testing;
4 In order to reduce maintenance costs, at some time prior to the incident, the company had approved a change of fuel from heavy fuel oil (HFO) to marine gas oil (MGO) for the heater, but the crew failed to make the necessary changes to the fuel pre-heating circuit and the auto-start programme;
5 Excessive diesel fuel entered the furnace which was probably at about the operating temperature (about 160 °C), and instantly vaporised (flash point ≈ 68 °C) and formed an explosive mixture with the charge air;
6 The crew failed to refer to the proper sources for advice on the treatment of burn injuries, resulting in the casualties being given inappropriate first aid (especially the deliberate puncturing of blisters);
7 The port’s contingency plan for responding to a vessel casualty and medical emergency in the anchorage lacked detailed documentation that would have ensured reliable information exchange among the concerned parties.

Corrective/preventative actions1 The ship’s operator renewed the burner units for both oil-fired heaters and altered the control system to better suit the fuel being used and the load demands placed on the heaters;
2 The heater’s makers reviewed and amended relevant sections of the equipment’s service manual and relayed the incident details to ancillary equipment suppliers, including the burner equipment manufacturer;
3 The port reviewed the emergency contingency plan and implemented revised procedures, including training, drills and exercises for its staff.

Lessons learnt1 Ship’s crew must remain vigilant to safety even when conducting repeated or seemingly simple tasks;
2 Manufacturers must provide comprehensive and accurate documentation for onboard service and maintenance and the crew must follow these along with the more generic procedures given in a ship’s SMS;
3 Manufacturers should conduct research and implement engineering solutions to resolve potential design weaknesses that may lead to failure or hazardous conditions in service;
4 It is desirable that critical items of equipment are serviced by specialist shore-based technicians, but if this is impracticable, ships’ crews must be given appropriate training arranged by the makers or suppliers of such equipment;
5 In case of illness or injury on board, ships’ crews must first refer to the approved publications carried onboard, if required, supplemented by correct radio medical advice obtained from shore. They must be capable of providing immediate and appropriate first aid. Burn injuries should always be immediately cooled, under clean, cold running water, for at least 10 minutes.
Diagrams for 201301

Photos for 201301
 

Sunday, January 12, 2014

Don't believe dockyard man. They can make U headache.

                               One Experience with shore repair

In our ship, M/E no. 3 unit coincide with PMS and Framo pump is also time to take maintenance. We requested for office we will overhauled M/E no.3 and because of insufficient time please send shore repair for Framo Pump. On the contrary, Office manage to overhauled M/E instead of Framo pump by shore repair company. In a nutshell, After overhauling M/E , the ship depart from Singapore to Korea. In pilotage way, there was no problem with M/E and everything was OK. After pilot away, M/E was to run in full away and we start increase speed gradually. In this M/E, MCR is 140 rpm . There was no problem until 120 rpm. But, when RPM is near 140, very loudly knocking sound is coming up in overhauled unit. Chief Engineer and First Engineer got head ache and thought probability and maintain M/E with 120 rpm and keep on sailing. In next port, we find fault and checked for hydraulic line for Exhaust valve, fuel pump and fuel system and mechanically looses. But we can not solve that problem till another port and finally, we notice that when we changed Exhaust valve, one" O" was lost in high pressure pipe for exhaust valve. We fitted with new spare " O" ring and problem is game over.

    Just one 'O" ring which they did not pay attention.



Fuel leakage from main engine fuel pump
A product tanker was proceeding on a long voyage after the completion of drydocking and associated surveys. During the ocean passage, the fire alarm suddenly activated in the engine room. Instead of a fire, the cause of the alarm turned out to be a large leakage of fuel oil from a flange on the inlet pipe of the main engine no. 4 fuel injection pump.

Result of investigation1 The fuel system had been overhauled, but no senior ship’s engineer supervised its refitting in drydock. As they did not have a new spare, the yard workers had reused the gasket of the flange connection on the suction side of the fuel injection pump even though it was damaged;
2 The insulation and leakage containment cover over the fuel line had not been renewed/refitted.
Lessons learnt1 Proper planning is necessary in drydock and during major repairs to ensure that responsible officers are delegated to supervise the refitting of critical components;
2 The condition, integrity and tightness of piping should be regularly checked, especially on critical equipment and fuel oil systems;
3 The vessel must ensure that adequate quantities of original spare parts are available at all times, and that all gaskets are renewed whenever pipelines are opened up and reconnected;
4 Wherever appropriate, lagging and containment covering must always be refitted, or renewed, if damaged;
5 All defective parts discovered after an incident must be carefully preserved to allow detailed investigations and to establish the underlying cause(s) so that effective corrective and preventative actions can be taken.
Fuel leakage

Hydraulic oil leak starts fire in engine room.If oil was sprayed on Exhaust manifold in anyhow, take a watch or make corrective action.

Hydraulic oil leak starts fire in engine room
On a tanker on passage, the fire alarm suddenly sounded. At the same time, the engine room crew saw small flames and smoke rising from the after exhaust manifold and cylinder heads of the running main engine. After extinguishing the localised fire, it was discovered that hydraulic oil from the cargo pump system had leaked from a flange connection in the vent/overflow line situated directly above the main engine cylinder head platform.

Result of investigation1 At the previous discharge port, a submerged cargo pump hydraulic motor had malfunctioned. In preparation for carrying out repairs, an engineer had closed the vent-cum-overflow line valve located before the service/header tank without draining the line;
2 Due to the residual pressure in the line, the flange connection (later found to have loose fasteners) leaked and a fine spray of hydraulic oil began falling on the hot surfaces on the top of the exhaust manifold and ignited after attaining self-ignition temperature.

Root cause/contributory factors1 Inadequate work planning – line was not depressurised/drained before closing of valve before header tank;
2 Inadequate management of change – the hydraulic piping had been modified some years ago to tap off a new branch line before the header tank leading to an offline oil filtering system. A stop valve was fitted before the branch without properly assessing risks;
3 Inadequate communication – the engineer who closed the valve failed to inform other members of this fact.

Corrective/preventative actions1 Ship’s staff removed the stop valve from the vent line, and the piping was re-modified to ensure that the offline filtration circuit was independent of the vent/overflow line;
2 All joints in the hydraulic system lines were inspected for proper condition and tightness;
3 Sister vessels fitted with the same filtration plant were advised to check the lines to ensure that the overflow line could not be inadvertently shut. All vessels were instructed to thoroughly inspect all nuts and bolts on flange joints and tighten them.
2013121
2013122



Comment: I don't understand about hydraulic system in this system. Anyway, If U touch the hydraullich system, first priority to think is how to release line pressure and to understand the system and follow the drawing.

Battery is a bomb if it was charged in excess current.

Battery damage caused by charger failure

 A ship’s engineer was carrying out planned maintenance of the emergency generator. When he started the generator, he heard a loud bang from the battery container. On investigating, he discovered that one of the starter batteries had exploded, with the top of the battery detaching from the body. The battery was safely removed and the engine was temporarily left in the manual starting mode.

On investigation, it was discovered that for an unknown period of time, the vessel’s emergency generator battery charging system was wrongly set up in such a way that two chargers could be charging the battery simultaneously. This resulted in excess evaporation of the water content in the electrolyte, substantially lowering the liquid level and exposing the plates. It is thought that internal arcing occurred across an air gap, triggering an explosion.

Lessons learnt1 All charging systems should be checked to ensure that the charging current cannot exceed the specified safe range;
2 All battery containers / receptacles should be checked for tightness of fixtures and overall integrity as part of planned maintenance.

Wrong installation of Limit switch which operates ventillation system was shared for intending for officers.

Pressure switch location for fire suppression systems
Source USCG Marine Safety Alert 05-12This safety alert addresses the location of fire suppression system pressure switches aboard vessels.

These critical components sense the activation of the system and then electrically secure the ventilation systems operating in the protected space. Securing the ventilation is essential in extinguishing a fire onboard a vessel. It assists in isolating the fire within the space, minimises the introduction of additional oxygen to fuel the fire and prevents the loss of fire suppression agents from the space.

Recently, a vessel with an installed fixed CO2 fire suppression system suffered extensive damage due to a fire that started in the engine room. During the firefighting efforts, the crew reported that the engine room ventilation could not be secured. A post-casualty damage survey of the vessel revealed that the pressure switch used to secure the ventilation was located within the engine room [see photographs of the damaged pressure switch and new switch.]

The Coast Guard strongly reminds owners and operators of vessels with installed fixed fire suppression systems to ensure that these switches are properly located aboard their vessels. If the pressure switch or switches are located within the space being protected, they should be relocated by a properly trained fire suppression service technician. Doing so will assist in ensuring system functionality and accessibility in the event of an emergency. Failing to do so could have serious
consequences to the vessel, its crew and the environment.

For the full safety alert go to http://www.uscg.mil/hq/cg5/TVNCOE/Documents/SafetyAlerts/PressureSwitch.pdf
201330 pressure switch location

Don't open the door after releasing CO2 within 24 or 48 hour although noticeably reduction in heat and smoke.

                    Premature reopening of fire area causes re-ignition
While underway a towing vessel with six crewmembers on board experienced an engine room fire. The chief engineer was in the engine room when the fire broke out. The only exit was an accommodation ladder which was in the path of the oil spray fire. The chief engineer exited through the fire, which ignited his clothing. The other crewmembers, who had also been alerted to the fire, discovered the chief engineer and extinguished the flames on his clothing. Nonetheless, the chief engineer suffered burns on more than 90 percent of his body.

As a first response, the crew released CO2 from the vessel’s fire suppression system into the engine room and extinguished the fire. After observing a noticeable reduction in heat and smoke, the Master reported that the fire was extinguished and crewmembers opened the doors to the vessel’s superstructure and began de-smoking it. However, this action compromised the fire boundary by allowing CO2 to escape and fresh air to enter the interior of the vessel, which caused the fire to reflash and rage out of control, consuming most of the tug’s superstructure. The crew had to abandon ship and were later rescued by SAR resources.

The vessel’s chief engineer was fatally injured, and the five remaining crewmembers suffered minor injuries.

Findings of the report
The engine room fire was probably caused by the ignition of lubricating oil that sprayed from a fatigue-fractured fitting on one of the main engine’s pre-lubrication oil pumps onto the hot surface of the main engine’s exhaust manifold.
* Contributing to the extent of the fire damage was the crewmembers’ compromise of the fire boundaries when they prematurely began de-smoking the vessel’s superstructure.
* The inability to completely secure the engine room’s fire boundaries also exacerbated the consequences of the fire.
* The abundance of flammable material throughout the vessel was also a contributing factor to the severity of the fire.

Editor’s Note: This is but one example of how the premature opening up of a fire scene can be disastrous. In my past activities as an accident investigator I have come across this same phenomenon on several occasions, especially for fires in the cargo hold. Essentially, once the fire area has been closed down and CO2 released, there is usually no overriding reason to open up until absolutely certain that all sources of heat have been eliminated. This can take time; up to 24 or even 48 hours. Another tip – if at all possible, do not open up until additional help can be mustered such as SAR resources or port facilities.

Never try to rescue someone without fully protecting yourself.



    Extra two men were dead by lack of knowledge.
A cargo ship was to discharge a cargo of copper sulphide concentrate and hatch covers of cargo holds No. 1 and No. 3 were opened to that end. Before discharge operations began, the stevedores had a safety meeting and discussed the unloading procedure. It was to be as follows:
1 Foreman has crew of the ship open hatch covers.
2 Foreman measures oxygen concentration in the holds.
3 Foreman opens entrance hatches of holds to be discharged and closes other hatches.
4 Foreman sets notice boards on entrance hatch.
5 The ship’s crane hoists the backhoe and carries it into hold.
6 Backhoe gathers cargo (copper concentrates) in the centre of hold.
7 Grab bucket of the on-shore crane grabs cargo and drops it into hopper.
8 Discharge the remaining cargo that the grab bucket cannot grab and collect using scoops and brooms.

Oxygen content was apparently measured at various points in both holds and found to be normal (20.9%). The driver of the backhoe for hold No. 3 entered the hold via an access hatch and went down a straight ladder (about 2.5m length), across a landing, and another slanting ladder (about 4m vertical). When he moved to the second landing, he fell feet-first, landed on his behind, and remained motionless. The crane operator who witnessed the fall put the backhoe down on the cargo pile and raised the alarm. He then got off the crane and ran to the entrance hatch of cargo hold No. 3.

Two stevedores entered the cargo hold through the entrance hatch leaving the self-contained breathing apparatus (SCBA) on the upper deck.

201367 1

Because they entered the cargo hold without SCBA, another stevedore followed them to prevent them from going down. When the third man had climbed halfway down the slanting ladder he felt breathless and one of the men in the hold signalled him to go back. He exited the hold, as did the man that signalled, but the third man had collapsed.

While the two men that had just exited the hold were catching their breath, crew of the ship provided them with gas masks. The canister attached to the gas mask indicated ‘Inorganic gases and vapours’. One stevedore, equipped with a gas mask and carrying the SCBA, headed for the hatch of cargo hold No. 3. The chief officer advised the stevedores that they should use the SCBA gear and that going into the hold with only gas masks is dangerous. Nonetheless, a stevedore equipped with the gas mask and carrying the SCBA on his back entered cargo hold No. 3 through the hatch again. At the time, the other stevedore could not understand the chief officer’s advice (spoken in English). He thought the mask might be an oxygen supply mask and as such, he too went into the hold with only the mask. When he climbed halfway down the slanting ladder he felt breathless and when he arrived at the second landing he felt faint. He turned back to the upper deck and used all his strength to crawl up the ladder. When he arrived near the hatch, the ship’s crew rescued him by pulling him up to upper deck by his arms. The other stevedore began to climb up the final ladder but fell into the hold after climbing one or two rungs. Now there were three casualties in the hold and rescue efforts to remove them would take time – too much time to save them.

The subsequent report found that oxygen in cargo hold No. 3 was consumed by the copper concentrate through oxidation. Some of the other findings of the report related to oxygen testing practices by the stevedore company were as follows:
1 Measurement locations were not standardised and often O2 concentration at the entrance hatch was not measured.
2 If the measured O2 concentration was less than 20.9%, measuring continued until it returned to 20.9%, hence it is not strange that all values in the record book were 20.9%.
3 If an entrance permitted notice board was exhibited on entrance hatch, stevedores entered the cargo hold even without permission of the cargo work supervisor.
4 The person measuring the O2 concentration did not inform the stevedores of the O2 concentration; the stevedores entered the cargo hold relying on the smell of the cargo and the entrance permitted notice board being displayed.
5 Usually, a stevedore was not very aware of the O2 concentration, but trusted the smell of the hold and his intuition.

Saturday, January 11, 2014

Accident at Incinerator's door

201402 Incinerator door deals a crushing blow

An engineer attempted to open the incinerator door while underway. His thumb was trapped and crushed between the door holder lever and the stopper plate (see photo). He was quickly transferred to the ship’s hospital and first aid was administered. The victim was disembarked and at the hospital a fracture of the thumb was diagnosed and orthopaedic surgery was necessary.

2014 02 01

2014 02 02

There were no reported difficulties in opening the door, and it is not known why the engineer placed his left hand at the indicated location. The engineer had two prior contracts with the same ship so he was familiar with this incinerator unit. However, the day before the incident there had been an unexpected engine room Unmanned Machinery Space (UMS) suspension. Due to this UMS suspension he had to stand watches in the engine room and as a consequence had inadequate rest for the period leading up to the accident.

Direct causes1 Inappropriate handling of the equipment.
2 Improper decision-making and lack of judgement.
3 Fatigue due to violation of resting hours the previous day without adequate compensatory rest.
Also, it appears the risks involved were not taken into consideration. Since the duties of operating the incinerator were considered ‘routine’, no risk assessment had been done on the task. Therefore, the company also found the following:

Contributing factors
4 Inappropriate management of engine staff.
5 Inadequate training and familiarisation.
6 Lack of a risk assessment on the use and handling of the incinerator.

Editor’s note: The company is to be congratulated for such a thorough report. It should be noted that the first two direct causes are in fact probably due to the third factor – fatigue. Fatigue has been said to be the equivalent of working while under the influence of alcohol, as both judgement and reaction time are impaired. In this case, the unexpected UMS suspension meant more work and less rest for the engineer. When unplanned extra work is incurred, mariners are encouraged to make every attempt to recuperate their needed rest hours to avoid unexpected negative consequences.



My comments.......

I don't want to translate above  report in Myanmar. Because Trying to understand in English will motivate you to reach many successful ways which we don't know.

 In Above this case,
One unconscious thing will make U in danger. Fourth Engineer put his hand on stopper in carelessness .

MARS 2013

MARS 2013

201349 Off-centre steering position confuses helm orders

Official Report edited from Canadian Transport Safety Board M11C0001
The vessel was downbound through a restricted waterway at night. At a lock, there was a change of pilots. Information was exchanged between pilots and the Master, among others, that the gyro-compass was 3° high. As the Master exchanged information with the new pilot, he assumed conning and operational control of the vessel.
The vessel’s pilot card showed a schematic of the navigating bridge that portrayed it as symmetrical either side of the centreline of the vessel. None of the documentation on the bridge indicated the important information pertaining to the conning and steering position, which was offset from the centreline. As it was, the steering stand was almost three metres to starboard of the centreline of the vessel. This resulted in a parallax error of approximately 1.6° to starboard if the line of sight is taken from the steering stand. The pilot was apparently aware that the steering stand was offset from the centreline, but had estimated the potential error to be about 0.5°.
Off-centre
Furthermore, the pilot card did not clearly indicate that the vessel was equipped with an articulated flap-type rudder, nor were the Master or other crew members apparently aware of this.
As the vessel cleared the lock the speed over the ground (SOG) was about 4 knots. The pilot then asked the Master to increase the pitch to 20% and requested the helmsman to steer on a heading of 353° gyro (G) to bring the vessel to the south of the channel centreline. This manoeuvre was standard practice to compensate for the flow coming from the regulating channel, starboard of the vessel. A few minutes later the pilot ordered the helmsman to steer on the light in the middle of the bridge span ahead to bring the vessel back towards the centre of the channel. At this time, Traffic Control also informed the bridge team that the bridge pillars immediately either side of the channel were not illuminated.
By this time the Master and the OOW were close to the pilot and observing the manoeuvre as the vessel proceeded at about 5.5 knots SOG. About one minute later the pilot gave the helmsman orders to bring the vessel’s head towards the north pillar of the bridge, which was not illuminated but was visible. Once the vessel was steadied on the pillar, the pilot found the heading to be 349.5°G and ordered the helmsman to steer 349°G (346° True). Since the course of the channel was 348°T, this heading would bring the vessel towards the centre more quickly. The pilot then reduced the pitch to 15%.

Shortly thereafter the pilot observed that the vessel was more to the south than expected, but this was not judged to be abnormal. He then reduced the pitch to 10% for the entry into the narrower part of the channel ahead. As the vessel entered the restricted part of the channel with a SOG of 6.8 knots and a heading of 350°G the helmsman had to apply starboard rudder to keep the vessel on the desired heading (an indication of bank suction astern). Shortly thereafter the vessel’s course took a sudden sheer to port. Immediately, the pilot ordered the rudder hard to starboard and requested that the Master activate the bow thruster. The pilot used the CP propeller lever to produce an engine kick ahead, then set the CP propeller lever at full astern but the vessel continued crossing the channel at a 45° angle.
The vessel’s bow subsequently grounded on the north bank of the channel some 0.75 nautical miles downstream from the lock they had just exited, the stern to the south side of the channel thereby blocking the waterway; vessel traffic was interrupted for approximately 10 hours until the vessel was successfully refloated.
Map
Some of the analysis and findings of the report indicate that:- Neither the offset steering stand from the centreline of the vessel nor specific and detailed information such as parallax error were provided to the pilot.

- On-board documentation did not clearly identify the vessel’s rudder type, nor were the bridge team members aware that the vessel was fitted with an articulated flap rudder.
Editor’s Note: Having a complete and detailed Pilot Card is crucial. Both the offset steering position and resulting parallax error as well as the articulated flap rudder are very important facts that should have been known to everyone involved. Yet, what was not mentioned in the official report was the apparent lack of complete communication between the bridge team, a critical element in good BRM. For example, the helmsman found he had to use more and more starboard helm to keep the required course, an early indication that the stern was experiencing bank suction. This fact should have been communicated to the pilot and Master/OOW instantly, thus giving advance warning of the onset of bank effect. This knowledge would have allowed countermeasures to be initiated before it was too late and the vessel took the sheer across the channel.